Moura - Waste Water Treatment Plant Upgrade

HomeMoura – Waste Water Treatment Plant Upgrade

Project Name:  
Moura Water Treatment Plant Upgrade

Client Name: Zinfra Infrastructure

Value: $ 750,000.00

Description:

BDR were awarded the mechanical installation of pipework, pumps and filters at the Moura WTP

Completed: December 2016

Challenges:

BDR maintained a steady balance between pre- fabrication and supply from our Brisbane based facility and delivery to site for installation on  a tight  project schedule.

Project completion was 6 weeks early and within the forecast budget.